About this Project
Program Overview:
The program, with a budget of $435 million, aims to replace GCRTA's 40 heavy railcars and 34 light railcars with 54 common railcars that can operate on both heavy and light rail systems. This approach will reduce the number of railcars needed and simplify maintenance. The new railcars will be safer, more reliable, technologically advanced, and will have a lower life-cycle cost. They are expected to serve the community for over 30 years and potentially increase ridership and stimulate transit-oriented development along the 33-mile rail system.
Current Railcars:
The Greater Cleveland Regional Transit Authority (GCRTA) is currently using heavy and light railcars that are 41 and 44 years old, respectively. These railcars are beyond their expected lifespan, leading to increased maintenance time and costs. Finding replacement parts is challenging due to their age, and the technology in these railcars is outdated.
Commissioning a New Railcar: the journey of a railcar
The commissioning process takes approximately 22 weeks (about five months) for the first few railcars as systems are validated and processes are established. As the process becomes more refined, subsequent railcars will move through commissioning more quickly.
Commissioning includes multiple stages of inspection and testing, such as:
- Delivery Inspection – approximately 2 days
- Static Testing – approximately 4 weeks
- Load Quality / Dynamic Testing – approximately 8 weeks, including testing of:
- Propulsion system
- Dynamic braking
- Wheel slip/slide protection
- Couplers
- Load leveling systems
- Ride quality
- Automatic Train Control (ATC) system
- 1,000 fault-free miles completed prior to final acceptance
These are examples of testing categories and are not an exhaustive list. Only after all required testing milestones are successfully completed can a railcar be certified for passenger service.
Frequently Asked Questions:
Why is GCRTA replacing its railcars?
What is the total cost of the Railcar Replacement Program?
The current program budget is $435 million. It includes:
- the design, manufacturing, and testing of the vehicles
- upgrades to the platforms
- upgrades to maintenance facilities
How much does each new railcar cost?
How is the project being funded?
The Railcar Replacement Program is funded through a combination of GCRTA funds, NOACA funds, and state and federal grants.
| Source | Amount | Percentage |
|---|---|---|
| GCRTA | $104.46M | 24.0% |
| Federal | $241.20M | 55.5% |
| ODOT | $60.54M | 13.9% |
| NOACA | $28.80M | 6.6% |
| TOTAL | $435.0M | 100.0% |
Why are new railcars arriving while GCRTA is facing budget and service challenges? Could this money be used for service or payroll instead?
Why is such a large investment necessary?
What are the benefits of the new railcars?
Progress and Milestones
-
Hatch begins designing with specscompleted
-
Siemens Mobility awarded railcar manufacturer
Base Order of 24 vehicles
completed -
Board approved exercising Option Order #01 for 6 additional vehicles
Brings the total order to 30 cars
completed -
Manufacturing for Car #01 beginscompleted
-
Board approved exercising Option Order #02 for 18 additional vehicles
Brings the total order to 48 cars
completed -
Brings the total order to 54 cars.
completed -
September 2026First railcar arrives in Cleveland
Additional railcars anticipated at a rate of approximately two per month until all 54 vehicles are delivered.
-
Summer 2027New cars enter revenue service on the Red Line
-
Summer 2028New cars enter revenue service on the Blue/Green/Waterfront Lines