About this Project
CLEVELAND -- The Greater Cleveland Regional Transit Authority (RTA) is planning to build a new station on the site of the current station at 2820 East 34th Street.
It is now called the Tri-C-Campus District Station. The station serves the Red Line, Green Line and Blue Line. Overall project budget is $7.5 million.
Public art
According to federal guidelines, the Station has a public art budget of $70,000. In March, RTA issued a call for artists to submit proposals. The proposals were submitted by May 8. RTA's Public Art Committee will review the proposals on May 31.
Funding
- 20 percent local
- 80 percent Federal, from 5 Capital Grants
- Total amount $6.015 million
Progress and Milestones
-
November 2014Community input
RTA holds 3 public meetings to gather community input on the future of the East 34th Street Station and two stations on East 79th Street. All have low ridership.
completed -
2015
RTA completed a Transit Service Alternative Analysis, to assess options to best serve this area. The conclusion and Board direction was to move ahead with station design, while working with the City of Cleveland and local development agencies to increase density and transit-oriented development (TOD) around the station. This would help ensure that investment in a new station would yield positive results.
completed -
Design contract Awarded
Board approved resolution 2015-78, and awarded a design contract to WPS (formerly known as Parsons Brinckerhoff) in an amount not to exceed $624,662.
completed -
Presented Design
Preliminary design presented to RTA Board of Trustees.
completed -
Updated presentation
Updated presentation on proposed station design.
completed -
Public Meeting
Public meeting is set to discuss proposed design.
completed -
January 2017Station Designcompleted
-
Construction contract awarded
RTA Board passes resolution 2017-22, and awards a $6.0 million construction contract to the Panzica Construction Co. of Mayfield Village. 80 percent of the work will be paid by the federal government. 12 Disadvantaged Business Enterprises (DBEs) will share 15 percent of the work, or $902,259.
completed -
Ground-breaking ceremonycompleted
-
June 2017Construction begins
Begin station construction. During construction, the Station will be closed to Red Line riders. Persons who need to use the Station can ride BlueLine / Green Line trains from stations at Tower City or East 55th Street.
completed -
Demolition
Most of the Red Line heavy-rail platform will close, as crews demolish a portion of the heavy-rail platform, and begin to install foundations for the new light-rail platform.
completed -
Service suspended
Service to the Red Line platform will be suspended.
completed -
April 2018Light-rail platform re-opened.completed
-
July 2018Red Line platform re-openedcompleted
-
September 2018New station opens